Sydney Water Facilities Renewal Panel

Client Sydney Water Location Sydney, NSW

The 5 year Program's objective is to deliver renewal works for Sydney Water’s infrastructure including water and sewage treatment plants, pumping stations and LV/HV electrical asset upgrades.

Key outcomes for the panel are to:

  • Continuously improve safety and performance
  • Support Sydney Water’s vision of providing ‘Valued Water Solutions’ at an affordable cost to customers
  • Build on Sydney Water’s strong performance in safety, environment, quality and customer outcomes

Projects delivered to date under the program include:

  • Cronulla WWTP Mechanical Renewals - package of mechanical renewals including:
    • Replacement of aeration diffusers and concrete remedial works in IDALs
    • Replacement of 750mm valves in the tertiary filters
  • Emu Plains Pump Station Upgrade - upgrade of water pump station including design, construction and commissioning of:
    • New high voltage pump including 11kV soft starter
    • Installation of all suction and delivery high pressure pipe work including construction of a new valve pit and thrust wall
    • Cut-in of the new pump into the existing system including coordination of all stakeholders to arrange required isolations
  • Pump Station Renewals - package of works for mechanical and electrical upgrade at four sewer pumping stations including:
    • Design, procurement, installation of new pumps, valves and pipework
    • Temporary works to bypass each pump station to enable works to proceed
    • Management of the community and environmental issues associated with delivery of the works